critical path

listen to the pronunciation of critical path
Английский Язык - Турецкий язык
(Mukavele) değişdiğinde proje bitiş tarihini direkt etkileyen proje başlangıcından bitimine kadar devamlı ardışık faaliyetler zinciri
critical path method
kritik yol yöntemi
critical path analysis
kritik gidişat analizi
critical path method
(CPM) kritik yol yöntemi
Английский Язык - Английский Язык
The sequence of dependent steps that determine the minimum time needed to carry out an operation
a way of planning and organizing a large piece of work so that there will be few delays and the cost will be as low as possible
The set of interrelated activities that must be completed for the project to be finished successfully can be mapped into a chart showing how long each task takes, and which tasks cannot be started before which other tasks are completed The critical path is the set of linkages through the chart that is the longest It determines how long a project will take
That path along a network plan which requires the greatest time for completion
When a project has several tasks, some of them overlapping or dependent upon earlier tasks, the critical path is the minimum time schedule for completing all the tasks The series of tasks that must be completed on schedule for a project to finish on schedule
The sequence of activities that must be completed on schedule for the entire project to be completed on schedule It is the longest duration path through the workplan If an activity on the critical path is delayed by one day, the entire project will be delayed by one day (unless another activity on the critical path can be accelerated by one day)
Plots the events that need to occur to complete a project on a timeline
schedule of activities which must be completed by particular dates in order for an entire project to be completed on time
Sequence of key tasks to be done by auction contractor or other designated parties on specified dates, leading to desired goals
the sequence and duration of tasks and activities which directly affect the date of overall project completion
A longest path in a network, where length units are time durations The nodes represent tasks, and the arcs represent precedence constraints The path is critical because the associated tasks determine the total completion time of the project Moreover, at least one of their duration times must decrease in order to decrease the total completion time
Method to determine the critical tasks based on relationships, duration and resource availability If any of the critical tasks is delayed the whole project will be delayed See also: Crashing the Critical Path
The set of activities that must be completed in sequence and on time if the entire project is to be completed on time
The sequence of interconnected events and activities between the start of a project and its completion that will require the longest time to accomplish This gives the shortest time in which the project can be completed; see also PERT
In a project network diagram, the series of activities which determines the earliest completion of the project The critical path will generally change from time to time as activities are completed ahead of or behind schedule Although normally calculated for the entire project, the critical path can also be determined for a milestone or subproject The critical path is usually defined as those activities with float less than or equal to a specified value, often zero See critical path method
The series of tasks which determines the earliest completion of the project, i e the longest sequence of tasks in the project; also defined as those tasks with float less than or equal to zero
The longest set of dependent activities in a project, not accounting for the resource constraint See the Project Management Institute's Project Management Body of Knowledge (PMBOK) or other project resources to understand critical path
The consecutive sequence of activities in a project whose cumulative time requirements determine the minimum total project time Delay in critical path activities delay the entire project if other steps are not compressed
In the context of GRADE, the most time-consuming sequence of tasks in a process
When a graph is used to model project scheduling, the critical path is a path from the start to the finish which passes through all of the tasks which are critical to completing the project in the shortest amount of time [refcomap, p 158]
(Ticaret) The consecutive sequence of activities in a project whose cumulative time requirements determine the minimum total project time. Delay in critical path activities delay the entire project if other steps are not compressed
The shortest time in which a project can be completed (3)
The sequence of events in a project that takes the longest to complete
A dependent sequence of activities in your project that takes the longest time to complete The critical path determines how long it will take to complete the project in the minimum time (Critical paths can change as your project unfolds)
The continuous chain of activities from project-start to project-finish, whose durations cannot be exceeded if the project is to be completed on the project-finish date A sequence of activities that collectively require the longest duration to complete (the duration of the sequence is the shortest possible time from the start event to the finish event) Activities on the critical path have no slack time
The series of activities that determines the duration of the project In a deterministic model, the critical path is usually defined as those activities with float less than or equal to a specified value, often zero It is the longest path through the project See critical path method
A term used in project planning to indicated a segment of the proposed work which if not completed on time will result in one or more other segments being delayed with serious "knock-on" effects for the project
A vital code path which should be optimised for the common case Critical paths are executed frequently and form the important trunk routes of various kernel operations An example would be buffer head manipulation during file I/O
critical path method
A network analysis technique used to predict project duration by analyzing which sequence of tasks has the least amount of scheduling flexibility (i e the least amount of float)
critical path method
A planning scheduling and control line and symbol diagram drawn to show the respective tasks and activities involved in constructing a specific project
critical path method
A quantitative technique which, when applied to network planning, is helpful in calculating the minimum time and sequence of tasks needed to complete a R & D project
critical path method
A network planning technique used for planning and controlling the activities in a project By showing each of these activities and their associated times, the 'critical path' can be determined The critical path is the series of successive activities which takes up most time and is therefore decisive for the total lead time of the project
critical path method
A management technique for losing your shirt under perfect control
critical path method
A network analysis technique used to predict project duration by analyzing which sequence of activities, (i e , which path), has the least amount of scheduling flexibility, (i e , the least amount of float) Early dates are calculated by means of a forward pass, using a specified start date Late dates are calculated by means of a backward pass, starting from a specified completion date for the project, (usually the forward pass' calculated early finish date)
critical path method
One of several techniques for doing project planning CPM can be used to plan a complex project that involves many activities
critical path method
A method of project schedule development which indicates flows of work and integrates individual schedule components
critical path method
a project management approach that shows the sequence of activities that define the minimum lead time needed to complete the project
critical path method
A network analysis technique used to predict project duration by analyzing which sequence of activities (which path) has the least amount of scheduling flexibility (the least amount of float) Early dates are calculated by means of a forward pass using a specified start date Late dates are calculated by means of a backward pass starting from a specified completion date (usually the forward pass’s calculated project early finish date)
critical path method
A technique used to predict project duration by analyzing which sequence of activities has the least amount of scheduling flexibility Early dates are figured by a forward pass using a specific start date and late dates are figured by using a backward starting from a completion date
critical path method
A method of network analysis in which normal duration is estimated for each activity within a project The critical path identifies the shortest completion period based on the most time-consuming sequence of activities from the beginning to the end of the network
critical path method
Critical path diagrams show the relationship between activities in a project
critical path

    Расстановка переносов

    cri·ti·cal path

    Турецкое произношение

    krîtîkıl päth

    Произношение

    /ˈkrətəkəl ˈpaᴛʜ/ /ˈkrɪtɪkəl ˈpæθ/
Избранное